City Engineers

The City of Valley City contracts with KLJ and Moore Engineering to serve as the city engineers.

Infrastructure Projects:

This page lists the current and upcoming infrastructure projects for the City of Valley City. Questions regarding project construction, please contact KLJ at (701) 845-4980. Questions regarding the financing of the project, including any estimated special assessments, please contact the City Auditor's Office at (701) 845-1700.

2nd Ave NW, 3rd St NW, and 4th St N Reconstruction Public Input Meeting

Virtual Presentation

Title VI Participation Survey

Sign-In Sheet

Project Updates

Construction Notice – 7th Street NW & 5th Avenue NW

Beginning Monday, April 22nd, 2024, the intersection of 5th Avenue NW and 7th Street NW will be closed for utility work in addition to the existing closures along 7th St NW and 6th St NW. No detour route will be provided. The intersection closure is anticipated to be in effect for 4 days, temporary surfacing will be placed in the intersection and it will be re-opened for traffic no later than Friday, April 26th, 2024.
Updated maps for all road closures will be posted on the City of Valley City’s webpage https://www.valleycity.us/engineers when they are taking affect. If you have any questions regarding the project, please contact Chad Petersen, KLJ Project Manager, at (701)-845-4980.

Construction Notice - Paving Improvement District 128 - 2nd Ave NW, 4th St NW/NE and 3rd St NW Street Reconstruction

Beginning Monday, April 15th, 2024, 3rd St NW will be closed from 2nd Ave NW to Central Ave N and 4th St NW/NE will be closed to through traffic from 2nd Ave NW to 2nd Ave NE, excluding the Central Ave N intersection. The closure will remain in effect until the Phase 1 portion of the corridor is reconstructed, which is anticipated to be early July 2024. The Phase 2 closure, including 2nd Ave NW from 2nd St NW to 4th St NW, will begin upon the completion of Phase 1 and is anticipated to be completed at the end of September 2024. Additional information regarding the Phase 2 work will be sent out at a later date. Phase 1 is defined as the work along 3rd St NW and 4th St NW/NE. Phase 2 is defined as the work along 2nd Ave NW.

The west alley between 3rd St NW and 4th St NW will be closed to through traffic, but alley access for businesses will be maintained from 2nd Ave NW during the closures. The east alley between 3rd St NE and 4th St NE will also have through traffic impacted during construction. Businesses will have access from 2nd Ave NE during the 4th St NE closure.

No detour route for motorized vehicles will be provided, temporary pedestrian access routes will be provided along the project route for the duration of the project, excluding the portion of work taking place on 4th St. NE.
Updated maps for all road closures will be posted on the City of Valley City’s webpage https://www.valleycity.us/engineers when they are taking affect. If you have any questions regarding the project, please contact Chad Petersen, KLJ Project Manager, at (701)-845-4980.

2024 Street & Infrastructure Reconstruction Projects w/ Preliminary Construction Timeline

11.6.2023 Construction Update #3 – Paving Improvement District 125 – 2nd Ave NE/4th St NE and 3rd St NE/3rd Ave NE Street Reconstruction

Phase 1: 2nd Ave NE continues to be closed to traffic from 2nd St NE to 5th St NE. Paving has been completed while concrete sidewalks and driveways are continuing to be worked. Concrete work is anticipated to be completed Week Ending November 11, 2023. Signing and temporary pavement parking are scheduled to be completed Week Ending November 18, 2023, weather pending. Upon completion of this work, the roadway will be opened to the public.

Updated maps for all road closures will be posted on the City of Valley City’s webpage https://www.valleycity.us/engineers when they are taking affect. If you have any questions regarding the project, please contact KLJ at (701)-845-4980.

Construction Update – Paving Improvement District 125 – 2nd Ave NE/4th St NE and 3rd St NE/3rd Ave NE Street Reconstruction

Phase 1: 2nd Ave NE continues to be closed to traffic from 2nd St NE to 5th St NE. No detour route for motorized vehicles will be provided, temporary pedestrian access routes are being provided.

Beginning Monday, August 7, 2023, work on 4th St NE will be extended east past the alley between 3rd St NE and 4th St NE. Access to properties along the alley will be provided from 3rd St NE. No access will be available from 4th St NE.  

If you have any questions regarding the project, please contact KLJ at (701)-845-4980.

Construction Notice – Update #1 – Paving Improvement District 125 – 2nd Ave NE/4th St NE and 3rd St NE/3rd Ave NE Street Reconstruction
Phase 1: 2nd Ave NE is closed to traffic from 2nd St NE to 5th St NE. The closure will remain in effect until the corridor is reconstructed, which is anticipated to be early October. No detour route for motorized vehicles will be provided, temporary pedestrian access routes will be provided along the project route for the duration of the project.
Beginning Monday, July 24, 2023, the intersection of 2nd Ave NE and 2nd St NE will be closed for utility work. This closure is anticipated to last approximately one week.
If you have any questions regarding the project, please contact KLJ at (701)-845-4980.

 

 

Comprehensive & Transportation Plan

The City of Valley City developed a Comprehensive & Transportation Plan to serve as a guide for growth and development through 2045. The plan was approved by City Commission on August 20, 2019 through Resolution No. 2216.

Valley City Permanent Flood Protection Map

Valley City Permanent Flood Protection Map provides details regarding location of installed permanent flood protection, planned permanent flood protection, and the floodway.

The Permanent Flood Protection (PFP) map shows the overall plan for permanent flood protection as planned to date (April 24, 2020). The existing floodplain is indicated on the map which shows the overall properties that will be protected with PFP.

Contact Us

KLJ - Valley City
1010 4th Avenue SW
Valley City, ND 58072
Phone: (701) 845-4980